Ch15 – s Supplement Advanced Methods for | Full Test Bank - Managing Operations Supply Chain 4e Complete Test Bank by Morgan Swink. DOCX document preview.

Ch15 – s Supplement Advanced Methods for | Full Test Bank

Chapter 15S Test Bank

Multiple Choice Questions

 

1. In evaluating time-cost trade-offs, we start by crashing the task on the critical path that:

 

A. Has the lowest cost to reduce by one unit of time.

B. Has the lowest total crash cost.

C. Can be reduced the most.

D. Is the longest.

E. None of these.

 

 

 

AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Remember
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 1 Easy
Topic: Project Crashing: Making Time-Cost Trade-Offs

 

2. Annie is planning a large surprise party for her sister Gwendolyn. She has developed the following plan, including estimates of the time (in hours) and cost necessary to perform each of the tasks required.

 

Task

Immediate Predecessor

Planned Duration

Minimum Duration

Crash Cost
per Hour

A. Create Guest List

--

8

4

$

27.50

B. Send Invitations

A

2

1

$

25.00

C. Buy Decorations

A

8

6

$

35.00

D. Plan Menu

A

3

2

$

60.00

E. Purchase Food

D

4

2

$

37.50

F. Prepare Food

E

5

3

$

125.00

 

What is the planned duration of the preparation for the surprise party, assuming the critical path is completed?

 

A. 16 hours

B. 8 hours

C. 20 hours

D. 30 hours

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 2 Medium
Topic: Project Crashing: Making Time-Cost Trade-Offs

 

3. Annie is planning a large surprise party for her sister Gwendolyn. She has developed the following plan, including estimates of the time (in hours) and cost necessary to perform each of the tasks required.

 

Task

Immediate Predecessor

Planned Duration

Minimum Duration

Crash Cost
per Hour

A. Create Guest List

--

8

4

$

27.50

B. Send Invitations

A

2

1

$

25.00

C. Buy Decorations

A

8

6

$

35.00

D. Plan Menu

A

3

2

$

60.00

E. Purchase Food

D

4

2

$

37.50

F. Prepare Food

E

5

3

$

125.00

 

Annie will save $40 for every hour she can reduce from her plan. Annie has decided to crash her project and use the money she saves to purchase a larger gift for Gwendolyn. Which task should she crash first?

 

A. A

B. D

C. C

D. E

E. B

 

 

 

AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Understand
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 2 Medium
Topic: Project Crashing: Making Time-Cost Trade-Offs

4. Annie is planning a large surprise party for her sister Gwendolyn. She has developed the following plan, including estimates of the time (in hours) and cost necessary to perform each of the tasks required.

 

Task

Immediate Predecessor

Planned Duration

Minimum Duration

Crash Cost
per Hour

A. Create Guest List

--

8

4

$

27.50

B. Send Invitations

A

2

1

$

25.00

C. Buy Decorations

A

8

6

$

35.00

D. Plan Menu

A

3

2

$

60.00

E. Purchase Food

D

4

2

$

37.50

F. Prepare Food

E

5

3

$

125.00

 

Annie will save $40 for every hour she can reduce from her plan. If Annie crashes only task A to its minimum duration, how much will she save on the project?

 

A. $55

B. $185

C. $160

D. $50

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 3 Hard
Topic: Project Crashing: Making Time-Cost Trade-Offs

5. Annie is planning a large surprise party for her sister Gwendolyn. She has developed the following plan, including estimates of the time (in hours) and cost necessary to perform each of the tasks required.

 

Task

Immediate Predecessor

Planned Duration

Minimum Duration

Crash Cost
per Hour

A. Create Guest List

--

8

4

$

27.50

B. Send Invitations

A

2

1

$

25.00

C. Buy Decorations

A

8

6

$

35.00

D. Plan Menu

A

3

2

$

60.00

E. Purchase Food

D

4

2

$

37.50

F. Prepare Food

E

5

3

$

125.00

 

If Annie has already crashed task A to its minimum duration, what is the next task she should crash?

 

A. A

B. C

C. E

D. F

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 2 Medium
Topic: Project Crashing: Making Time-Cost Trade-Offs

6. Annie is planning a large surprise party for her sister Gwendolyn. She has developed the following plan, including estimates of the time (in hours) and cost necessary to perform each of the tasks required.

 

Task

Immediate Predecessor

Planned Duration

Minimum Duration

Crash Cost
per Hour

A. Create Guest List

--

8

4

$

27.50

B. Send Invitations

A

2

1

$

25.00

C. Buy Decorations

A

8

6

$

35.00

D. Plan Menu

A

3

2

$

60.00

E. Purchase Food

D

4

2

$

37.50

F. Prepare Food

E

5

3

$

125.00

 

If Annie saves $40 for every hour she can reduce from her plan, what is her total net benefit from crashing this project by six hours?

 

A. $55

B. $185

C. $160

D. $240

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 3 Hard
Topic: Project Crashing: Making Time-Cost Trade-Offs

7.   

Task

Immediate Predecessor

Planned Duration

Minimum Duration

Crash Cost per Hour

A

--

10

8

$

250

 

B

A

16

4

$

400

 

C

A

12

9

$

100

 

D

B,C

17

16

$

300

 

E

B

14

13

$

300

 

F

D,E

6

2

$

350

 

 

C:\fake\image0.png

 

Identify the critical path to completion for the project plan.

 

A. A, C, D, F is 45 hours.

B. A, B, C, D, E, F is not a path.

C. A, B, E, F is 46 hours.

D. A, B, D, F is 49 hours

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 3 Hard
Topic: Project Crashing: Making Time-Cost Trade-Offs

8.

Task

Immediate Predecessor

Planned Duration

Minimum Duration

Crash Cost per Hour

A

--

10

8

$

250

 

B

A

16

4

$

400

 

C

A

12

9

$

100

 

D

B,C

17

16

$

300

 

E

B

14

13

$

300

 

F

D,E

6

2

$

350

 

 

C:\fake\image1.png

 

If there is a desire to crash the project, which task should be crashed first?

 

A. A

B. B

C. D

D. F

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 2 Medium
Topic: Project Crashing: Making Time-Cost Trade-Offs

9.

Task

Immediate Predecessor

Planned Duration

Minimum Duration

Crash Cost per Hour

A

- -

10

8

$

250

 

B

A

16

4

$

400

 

C

A

12

9

$

100

 

D

B,C

17

16

$

300

 

E

B

14

13

$

300

 

F

D,E

6

2

$

350

 

 

C:\fake\image2.png

 

If the project is crashed so that all work can be completed in 45 hours, what is the total crash cost?

 

A. $650

B. $950

C. $1,150

D. $1,450

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 3 Hard
Topic: Project Crashing: Making Time-Cost Trade-Offs

10. A project manager has discovered that three tasks are on the critical path for a particular project. She has developed the time estimates (in days) shown in the table below. Complete the table and determine the expected completion time for the project.

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

5

8

14

 

 

 

B

2

4

9

 

 

 

C

3

5

7

 

 

 

 

A. 17 days

B. 18 days

C. 21 days

D. 19 days

 

 

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

5

8

14

(5 + 8 × 4 + 14)/6 = 8.5

(14 − 5)/6 = 1.5

2.25

B

2

4

9

4.5

1.167

1.36

C

3

5

7

5.0

.667

.444

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 1 Easy
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

11. A project manager has discovered that three tasks are on the critical path for a particular project. She has developed the time estimates (in days) shown in the table below. Complete the table and determine the probability that the project will be completed in 20 days or less.

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

5

8

14

 

 

 

B

2

4

9

 

 

 

C

3

5

7

 

 

 

 

A. Approximately 92 percent

B. Approximately 88 percent

C. Approximately 75 percent

D. Approximately 84 percent

 

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

5

8

14

(5 + 8 × 4 + 14)/6 = 8.5

(14 − 5)/6 = 1.5

2.25

B

2

4

9

4.5

1.167

1.36

C

3

5

7

5.0

.667

.444

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

12. A project manager has discovered that three tasks are on the critical path for a particular project. She has developed the time estimates (in days) shown in the table below.

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

5

8

14

 

 

 

B

2

4

9

 

 

 

C

3

5

7

 

 

 

 

The customer has offered a $10,000 bonus if the project is completed within 14 days. What is the probability that the bonus will be earned?

 

A. Approximately 85 percent

B. Approximately 5 percent

C. Approximately 2.3 percent

D. Approximately 97.7 percent

 

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

5

8

14

(5 + 8 × 4 + 14)/6 = 8.5

(14 − 5)/6 = 1.5

2.25

B

2

4

9

4.5

1.167

1.36

C

3

5

7

5.0

.667

.444

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

13. A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

2

3

4

 

 

 

B

1

1.5

2

 

 

 

C

.5

1

1.5

 

 

 

D

1.5

2

2.5

 

 

 

E

.5

1

1.5

 

 

 

F

.4

.5

.6

 

 

 

 

What is the expected total time for the project?

 

A. 7.33 days

B. 9.00 days

C. 10 days

D. 12.67 days

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 2 Medium
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

14. A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

2

3

4

 

 

 

B

1

1.5

2

 

 

 

C

.5

1

1.5

 

 

 

D

1.5

2

2.5

 

 

 

E

.5

1

1.5

 

 

 

F

.4

.5

.6

 

 

 

 

What is the likelihood the project will be completed in 10 days?

 

A. Between 88 and 88 percent

B. Between 89 and 92 percent

C. Between 93 and 97 percent

D. Between 98 and 100 percent

 

 

Activity

Predecessor

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

-

2

3

4

3

.33

.1089

B

A

1

1.5

2

1.5

.17

.0289

C

B

.5

1

1.5

1

.17

.0289

D

C

1.5

2

2.5

2

.17

.0289

E

D

.5

1

1.5

1

.17

.0289

F

E

.4

.5

.6

.5

.03

.0011

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

15. A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:

 

Task

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

2

3

4

 

 

 

B

1

1.5

2

 

 

 

C

.5

1

1.5

 

 

 

D

1.5

2

2.5

 

 

 

E

.5

1

1.5

 

 

 

F

.4

.5

.6

 

 

 

 

What is the probability that the project will be completed within 8.5 days? (Choose the closest answer.)rev: 08_07_2017_QC_CS-95018

 

A. 80 percent

B. 15 percent

C. 75 percent

D. 5 percent

 

 

Activity

Predecessor

Best Case

Most Likely

Worst Case

Expected Duration

Standard Deviation

Standard Deviation Squared

A

-

2

3

4

3

.33

.1089

B

A

1

1.5

2

1.5

.17

.0289

C

B

.5

1

1.5

1

.17

.0289

D

C

1.5

2

2.5

2

.17

.0289

E

D

.5

1

1.5

1

.17

.0289

F

E

.4

.5

.6

.5

.03

.0011

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

16. Which of the following statements best describes "crash cost"?

 

A. Estimated cost to reduce a project task duration by one time unit.

B. Estimated cost to reduce a project duration by one time unit.

C. Estimated cost to reduce the project schedule by one time unit.

D. Actual cost to reduce a project duration by one time unit.

E. Actual cost to change a project schedule.

 

 

 

AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Remember
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 1 Easy
Topic: Project Crashing: Making Time-Cost Trade-Offs

 

17. Given the tasks, estimated durations, and crash costs shown below, what is the total cost of the steps needed to provide the cheapest way to reduce the project length by three days?

 

Task

Predecessors

Estimated duration (days)

Crash cost
per day

Number of days task can be crashed

A

none

2

$

1000

 

2

B

A

3

$

400

 

1

C

A

3

$

300

 

2

D

B,C

4

$

800

 

1

E

D

3

Cannot be crashed

0

 

A. $2,800

B. $2,500

C. $1,100

D. $2,300

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 2 Medium
Topic: Project Crashing: Making Time-Cost Trade-Offs

18. Given the tasks, estimated durations, and crash costs shown below, if the benefit to crash the project by each day is a maximum of $750, how many days would it be worthwhile to crash the project?

 

Task

Predecessors

Estimated duration (days)

Crash cost
per day

Number of days task can be crashed

A

none

2

$

1000

 

2

B

A

3

$

400

 

1

C

A

3

$

300

 

2

D

B,C

4

$

800

 

1

E

D

3

Cannot be crashed

0

 

A. 0

B. 1

C. 2

D. 3

E. 4

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 2 Medium
Topic: Project Crashing: Making Time-Cost Trade-Offs

 

19. Which of the following statements is true regarding crash costs?

 

A. Crash costs tend to increase with each additional day of crashing.

B. Crash costs tend to decrease with each additional day of crashing.

C. It is usually cheaper to crash tasks that are not on the critical path.

D. Additional crash costs are rarely justified in practice.

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 3 Hard
Topic: Project Crashing: Making Time-Cost Trade-Offs

20. An estimate of the duration of a task that is based on a weighted average of a range of possible task durations is known as:

 

A. Most likely duration.

B. Expected duration.

C. Worst-case duration.

D. Probabilistic duration.

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Remember
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 1 Easy
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

 

21. Task X has a best-case duration of 4 days, a worst-case duration of 10 days, and a most likely duration of 6 days. Using this information, we can estimate a 50 percent probability that the task will be completed in no more than how many days?

 

A. 6.0 days

B. 3.3 days

C. 10.0 days

D. 6.3 days

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 2 Medium
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

22. Given the project data below, what is the expected length of path A, B, C?

 

Task

Predecessors

Best Case

Most Likely case

Worst Case

A

None

2

4

6

B

A

1

4

5

C

B

.5

1

6

 

A. 9.0

B. 9.8

C. 9.4

D. 17

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 2 Medium
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

 

23. Given the project data below, what is the standard deviation of durations for path A, B, C?

 

Task

Predecessors

Best Case

Most Likely case

Worst Case

A

None

2

4

6

B

A

1

4

5

C

B

.5

1

6

 

A. 1.3

B. 2.3

C. 1.7

D. None of the choices are correct

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

24. If a project path has an expected duration of 10 days and a standard deviation of three days, what is the probability that the path will be completed in 10 days or less?

 

A. 0 percent

B. 33 percent

C. 50 percent

D. 75 percent

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

 

25. If a project path has an expected duration of 10 days and a standard deviation of three days, what is the probability that the path will be completed in 13 days or less?

 

A. 50 percent

B. 33 percent

C. 75 percent

D. 84 percent

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

26. Given the project plan shown below, for each task assume that the best-case duration is 80 percent of the most likely duration, and the worst-case duration is 150 percent of the most likely duration. What is the expected completion time for the critical path?

 

Task ID

Immediate Predecessors

Most Likely duration (days)

A

-

4

B

-

5

C

-

6

D

A,B,C

5

E

D

7

F

D

4

G

E,F

3

 

A. 34 days

B. 21.0 days

C. 35.7 days

D. 22.1 days

 

 

 

a = .8m

m

b = 1.5m

(a + 4m + b)/6

 

 

Best case

Most likely

Worst case

Expected

Critical path

A

3.2

4

6

4.2

 

B

4

5

7.5

5.25

 

C

4.8

6

9

6.3

6.3

D

4

5

7.5

5.25

5.25

E

5.6

7

10.5

7.35

7.35

F

3.2

4

6

4.2

 

G

2.4

3

4.5

3.15

3.15

 

Total duration

35.7

22.05

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

27. The four tasks below must be completed in order (a single path of tasks). Given the task information, what is the probability that the path of tasks will be completed in 20 days or less?

 

Task number

Expected duration (days)

Standard deviation of duration (days)

1

5

2

2

3

1

3

4

2

4

5

3

 

A. 34 percent

B. 56.4 percent

C. 50 percent

D. 76.0 percent

 

 

Task number

Expected duration (days)

Standard deviation of duration (days)

Variance = std dev2

1

5

2

4

2

3

1

1

3

4

2

4

4

5

3

9

Total

17

4.24

18

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

28. Given the project plan shown below, which task has the largest standard deviation (uncertainty) relative to its expected duration (standard deviation divided by expected duration)?

 

Task ID

Immediate Predecessors

Most likely duration (days)

Best-case duration (days)

Worst-case duration (days)

A

-

4

3

7

B

-

5

2

8

C

-

6

6

9

D

A,B,C

5

3

8

E

D

7

6

9

F

D

4

2

5

G

E,F

3

2

4

 

A. Task A

B. Task B

C. Task D

D. Task G

 

 

Task ID

Immediate Predecessors

Most likely duration (days)

Best-case duration (days)

Worst-case duration (days)

Expected
(a + 4m + b)/6

Std dev (b − a)/6

Std Dev/expected

A

-

4

3

7

4.33

0.67

0.154

B

-

5

2

8

5

1

0.2

C

-

6

6

9

6.5

0.5

0.077

D

A,B,C

5

3

8

5.17

0.83

0.161

E

D

7

6

9

7.17

0.5

0.07

F

D

4

2

5

3.83

0.5

0.13

G

E,F

3

2

4

3

0.33

0.111

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

29. Task X has a most likely duration of 10 days, a best-case duration of 8 days, and a worst-case duration of 15 days.  What is the probability that it will be completed in 12 days or less?

 

A. 0 percent

B. 95.7 percent

C. 90.1 percent

D. 75.3 percent

 

 

Most likely duration (days)

Best-case duration (days)

Worst-case duration (days)

Expected
(a + 4m + b)/6

Std dev (b − a)/6

10

8

15

10.50

1.17

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

 

30. Task X has a most likely duration of 10 days, a best-case duration of 8 days, and a worst-case duration of 15 days.  What is the probability that it will be completed in 10 days or less?

 

A. 0 percent

B. 50.0 percent

C. 33.4 percent

D. 83.4 percent

 

 

Most likely duration (days)

Best-case  duration (days)

Worst-case duration (days)

Expected
(a + 4m + b)/6

S= (12 −– 10.5)/1.17 = 1.29;  from Z table, probability is 90.07% percenttd dev (b − a)/6

10

8

15

10.50

1.17

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

31. Task X has an 82 percent probability that it will be completed in 20 days or less. The standard deviation of its duration is five days. What is its expected duration?

 

A. 15.4 days

B. 15.9 days

C. 19.1 days

D. 12.3 days

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 3 Hard
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

 

32. Given the tasks, estimated durations, and crash costs shown below, which task would you crash first?

 

Task

Predecessors

Estimated duration (days)

Crash cost per day

A

-

1

$

1,000

B

A

5

$

500

C

A

3

$

200

D

B, C

2

$

800

E

D

7

$

700

 

A. Task A

B. Task B

C. Task C

D. Task D

E. Task E

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Understand
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 2 Medium
Topic: Project Crashing: Making Time-Cost Trade-Offs

33. Given the tasks, estimated durations, and crash costs shown below, which task would you crash last in order to minimize the project length?

 

Task

Predecessors

Estimated duration (days)

Crash cost per day

Number of days task can be crashed

A

-

1

$

1,000

1

B

A

5

$

500

1

C

A

3

$

1,200

2

D

B, C

2

$

800

1

E

D

7

$

700

1

 

A. Task A

B. Task B

C. Task C

D. Task D

E. Task E

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Understand
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 1 Easy
Topic: Project Crashing: Making Time-Cost Trade-Offs

 

34. Given the tasks, estimated durations, and crash costs shown below, what would be the minimum cost to reduce the project by one day?

 

Task

Predecessors

Estimated duration (days)

Crash cost per day

Number of days task can be crashed

A

-

1

$

1,000

2

B

A

5

$

500

1

C

A

5

$

200

2

D

B, C

2

$

900

1

E

D

7

$

800

1

 

A. $200

B. $500

C. $700

D. $800

E. $1,000

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Blooms: Analyze
Gradable: automatic
Learning Objective: 15S-01 Make time and cost trade-offs in projects.
Level of Difficulty: 3 Hard
Topic: Project Crashing: Making Time-Cost Trade-Offs

 

35. For a project with many task paths of nearly equal lengths, the best way to estimate the probabilities associated with project completion is:

 

A. Estimate the probability for the critical path

B. Multiply the probabilities of all paths

C. Use simulation to model the project

D. Calculate the joint probability of project completion

 

 

 

AACSB: Analytical Thinking
Accessibility: Keyboard Navigation
Accessibility: Screen Reader Compatible
Blooms: Remember
Gradable: automatic
Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.
Level of Difficulty: 1 Easy
Topic: Scheduling a Project with Probabilistic Task Duration Estimates

Chapter 15S Test Bank - Static Summary

Category

# of Questions

AACSB:  Analytical Thinking

32

AACSB:  Reflective Thinking

3

Accessibility: Keyboard Navigation

35

Accessibility: Screen Reader Compatible

8

Blooms: Analyze

28

Blooms: Remember

4

Blooms: Understand

3

Gradable: automatic

35

Learning Objective: 15S-01 Make time and cost trade-offs in projects.

16

Learning Objective: 15S-02 Schedule projects using probabilistic task time estimates.

19

Level of Difficulty: 1 Easy

6

Level of Difficulty: 2 Medium

10

Level of Difficulty: 3 Hard

19

Topic: Project Crashing: Making Time-Cost Trade-Offs

16

Topic: Scheduling a Project with Probabilistic Task Duration Estimates

19

Document Information

Document Type:
DOCX
Chapter Number:
15s
Created Date:
Aug 21, 2025
Chapter Name:
Chapter 15s Supplement Advanced Methods for Project Scheduling
Author:
Morgan Swink

Connected Book

Managing Operations Supply Chain 4e Complete Test Bank

By Morgan Swink

Test Bank General
View Product →

$24.99

100% satisfaction guarantee

Buy Full Test Bank

Benefits

Immediately available after payment
Answers are available after payment
ZIP file includes all related files
Files are in Word format (DOCX)
Check the description to see the contents of each ZIP file
We do not share your information with any third party