Full Test Bank Ch17 Scheduling - Operations Management 2e Canadian Test Bank by Roberta S. Russell. DOCX document preview.
CHAPTER 17
SCHEDULING
CHAPTER LEARNING OBJECTIVES
1. Describe scheduling techniques and list the objectives of scheduling. Scheduling techniques vary by type of production process. Scheduling in a job shop environment is difficult because jobs arrive at varying time intervals, require different resources and sequences of operations, and are due at different times. This lowest level of scheduling is referred to as shop floor control or production control. It involves assigning jobs to machines or workers (called loading), specifying the order in which operations are to be performed, and monitoring the work as it progresses. There are many objectives in constructing a schedule—some of which may conflict:
• Meeting customer due dates
• Minimizing job lateness
• Minimizing response time
• Minimizing completion time
• Minimizing time in the system
• Minimizing overtime
• Maximizing machine or labour use
• Minimizing idle time
• Minimizing work-in-process inventory
2. Explain what loading is and use the assignment method to load work on to limited resources. Loading is the process of assigning work to limited resources. The assignment method is a specialized linear programming solution procedure for deciding which worker to assign to a task, or which job to assign to a machine. The procedure creates an opportunity cost matrix and selects the best assignment in consideration of trade-offs among alternatives. See Section 17.2 for an example of the assignment method.
3. Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations. Sequencing is the process of prioritizing jobs and determining the processing order. See Section 17.3 for examples of sequencing jobs through one or two workstations.
4. Use several methods to monitor the progress of jobs in a job shop environment. Gantt charts can be used to monitor a job’s progress against the plan, and input/output controls monitor the input to and output from each work centre.
5. Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations. Realistic schedules must reflect capacity limitations. Infinite scheduling initially assumes infinite capacity and then manually “levels the load” of resources that have exceeded capacity. Finite scheduling loads jobs in priority order and delays those jobs for which current capacity is exceeded. The theory of constraints is a finite scheduling approach that schedules bottleneck resources first and then schedules other resources to support the bottleneck schedule. It also allows items to be transferred between resources in lot sizes that differ from the lot size in which the item is produced. Other advanced planning and scheduling techniques include mathematical programming, genetic algorithms, and simulation.
6. Use a heuristic to schedule workers and explain the capabilities provided by employee scheduling software. Employee scheduling is often difficult because of the variety of options available and the special requirements for individual workers. Scheduling heuristics are typically used to develop patterns of worker assignment (see Example 17.2 for an example). Automated workforce scheduling systems are becoming more commonplace. Scheduling software:
• Assigns qualified workers to standardize shift patterns, taking into account leave requests and scheduling conflicts
• Allows workers to bid on certain shifts and post and trade schedules
• Creates demand-driven forecasts of labour requirements and assigns workers to variable schedules that change dynamically with demand
TRUE-FALSE STATEMENTS
1. Scheduling specifies when labour, equipment and facilities are needed to produce a product.
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
AACSB: Reflective Thinking
2. Scheduling is considered the last stage of the planning process.
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking
3. The wide variety of jobs in a job shop makes scheduling difficult.
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking
4. Managers typically use multiple objectives when constructing a schedule.
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking
5. Minimizing overtime is one of several objectives that could be considered when constructing a schedule.
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking
6. Job-shop scheduling is usually performed by skilled machine operators.
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking
7. Gantt charts show the planned and yet to be completed activities against total activities.
Difficulty: Medium
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
AACSB: Reflective Thinking
8. The scheduling function for mass production and job shop production are basically the same.
Difficulty: Medium
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Comprehension
AACSB: Reflective Thinking
9. Job shop scheduling is also known as shop floor control.
Difficulty: Medium
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking
10. The process of assigning work to limited resources is known as scheduling.
Difficulty: Medium
Learning Objective: Explain what loading is and use the assignment method to load work on to limited resources.
Section Reference: 17.2 Loading
Blooms: Knowledge
AACSB: Reflective Thinking
11. Sequencing involves determining the order in which jobs are released to the shop floor.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
12. The sequence in which jobs should be processed is determined by using the linear programming.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
13. Determining the optimal allocation of jobs to machines or workers can be solved using the assignment method of linear programming.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
14. The process of prioritizing jobs that have been assigned to a resource is called sequencing.
Difficulty: Easy
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Knowledge
AACSB: Reflective Thinking
15. The time required for a job to move through the system is referred to as flow time.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Knowledge
AACSB: Reflective Thinking
16. All sequencing rules strive to optimize both processing efficiency and due date performance.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
17. Johnson’s rule gives an optimal sequence for jobs processed serially through a two step system.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
18. The shortest processing time (SPT) rule is most useful when the job shop is not congested.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
19. The longest processing time (LPT) rule tends to complete larger jobs in-house when subcontracting is anticipated.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
20. The first-come, first-served (FCFS) sequencing rule should be only used when operating at high levels of capacity.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
21. The dispatch list contains the order in which the work is assigned to a productive resource.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
22. In a job shop environment, the process of prioritizing jobs assigned to a productive resource is called sequencing.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
23. Tardiness is defined as the difference between a job’s flow time and makespan.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
24. Input/output control provides the information necessary to regulate work flow in a job shop environment.
Difficulty: Medium
Learning Objective: Use several methods to monitor the progress of jobs in a job shop environment.
Section Reference: 17.4 Monitoring
Blooms: Comprehension
AACSB: Reflective Thinking
25. Increasing the capacity of a work centre that is a bottleneck increases the output.
Difficulty: Medium
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Comprehension
AACSB: Reflective Thinking
26. Finite scheduling will not load a resource beyond its fixed capacity.
Difficulty: Medium
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Comprehension
AACSB: Reflective Thinking
27. The theory of constraints (TOC) approach to scheduling concentrates on scheduling the bottleneck resources.
Difficulty: Medium
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Comprehension
AACSB: Reflective Thinking
28. With drum-buffer-rope (DBR), the bottleneck resource is always the buffer.
Difficulty: Medium
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Comprehension
AACSB: Reflective Thinking
29. Scheduling using the theory of constraints (TOC) requires that the process batch sizes and the transfer batch sizes always match.
Difficulty: Medium
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Comprehension
AACSB: Reflective Thinking
30. Typically, there are more options available when scheduling employees because labour is a very flexible resource.
Difficulty: Medium
Learning Objective: Use a heuristic to schedule workers and explain the capabilities provided by employee scheduling software.
Section Reference: 17.6 Employee Scheduling
Blooms: Knowledge
AACSB: Reflective Thinking
31. The assignment method of linear programming can be used for both the loading and employee scheduling.
Difficulty: Medium
Learning Objective: Use a heuristic to schedule workers and explain the capabilities provided by employee scheduling software.
Section Reference: 17.6 Employee Scheduling
Blooms: Knowledge
AACSB: Reflective Thinking
MULTIPLE CHOICE QUESTIONS
32. Which of the following is not typically considered an objective of scheduling?
a) minimizing job lateness
b) maximizing time in the system
c) minimizing overtime
d) maximizing machine utilization
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking
33. The process of smoothing out the work assigned is known as
a) production control
b) sequencing
c) load levelling
d) dispatching
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking
34. The process of assigning work to limited resources is known as
a) loading.
b) sequencing.
c) monitoring.
d) dispatching
Difficulty: Easy
Learning Objective: Explain what loading is and use the assignment method to load work on to limited resources.
Section Reference: 17.2 Loading
Blooms: Knowledge
AACSB: Reflective Thinking
35. Which of the following is not part of the procedure for a minimization problem under the assignment method of loading?
a) performing row reductions
b) performing column reductions
c) developing a constraint matrix
d) developing an opportunity cost matrix
Difficulty: Medium
Learning Objective: Explain what loading is and use the assignment method to load work on to limited resources.
Section Reference: 17.2 Loading
Blooms: Comprehension
AACSB: Reflective Thinking
36. The process of prioritizing jobs that have been assigned to a resource is called
a) loading.
b) monitoring.
c) sequencing.
d) input/output analysis.
Difficulty: Easy
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Knowledge
AACSB: Reflective Thinking
37. If a job is ahead of schedule, then its critical ratio (CR) will be
a) less than one.
b) greater than one.
c) equal to one.
d) none of the above.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Reflective Thinking
38. If the work remaining is greater than the time remaining, the critical ratio (CR) will be
a) less than one.
b) greater than one.
c) equal to one.
d) none of the above.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Reflective Thinking
39. The time required to complete a group of jobs is referred to as
a) flow time.
b) makespan.
c) completion time.
d) none of the above.
Difficulty: Easy
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Knowledge
AACSB: Reflective Thinking
40. The sequencing rule that will minimize average job completion time for a set number of jobs to be processed on one machine is
a) first-come-first served (FCFS).
b) longest processing time (LPT).
c) shortest process time (SPT).
d) due date (DDATE).
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Reflective Thinking
41. The sequencing rule that minimizes average tardiness for a set of jobs to be processed on one machine is
a) first-come-first served (FCFS).
b) longest processing time (LPT).
c) shortest process time (SPT).
d) due date (DDATE).
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
42. If the following jobs are sequenced according to the first-come-first-served (FCFS) rule, then the mean completion time in days for all jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 33 days.
b) 22 days.
c) 6.6 days.
d) 4.4 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
43. If the following jobs are sequenced according to the FCFS rule, then the mean tardiness (in days) for all jobs would be (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 5 days.
b) 8.33 days.
c) 10.6 days.
d) 25 days
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
44. If the following jobs are sequenced according to the FCFS rule, then the maximum job tardiness (in days) is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 0 days.
b) 8 days.
c) 20 days.
d) 25 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
45. If the following jobs are sequenced according to the FCFS rule, then the total number of jobs that would be late is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 4.
b) 3.
c) 2.
d) 1.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
46. If the following jobs are sequenced according to the FCFS rule, then job C is completed on day (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 11.
b) 17.
c) 25.
d) 30.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
47. If the following jobs are sequenced according to the SPT rule, then the mean completion time (in days) for all the jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 6.6 days.
b) 16 days.
c) 22 days.
d) 33 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
48. If the following jobs are sequenced according to the SPT rule, then the mean tardiness (in days) for all the jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 16 days.
b) 13 days.
c) 5.2 days.
d) 3.2 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
49. If the following jobs are sequenced according to the SPT rule, then the maximum job tardiness (in days) is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 26 days.
b) 16 days.
c) 10 days.
d) 5.2 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
50. If the following jobs are sequenced according to the SPT rule, then the total number of jobs that would be late is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 0 jobs.
b) 1 job.
c) 2 jobs.
d) 3 jobs.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
51. If the following jobs are sequenced according to the SPT rule, then job B is completed on day (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 6.
b) 14.
c) 15.
d) 22.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
52. If the following jobs are sequenced according to the LPT rule, then the mean completion time (in days) for all jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 118 days.
b) 6.6 days.
c) 33 days.
d) 23.6 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
53. If the following jobs are sequenced according to the LPT rule, then the mean tardiness (in days) for all jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 62 days.
b) 12.4 days.
c) 15.5 days.
d) 25 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
54. If the following jobs are sequenced according to the LPT rule, then the maximum job tardiness (in days) is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 7 days.
b) 10 days.
c) 20 days.
d) 25 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
55. If the following jobs are sequenced according to the LPT rule, then the total number of jobs that would be late is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 5 jobs.
b) 4 jobs.
c) 3 jobs.
d) 2 jobs.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
56. If the following jobs are sequenced according to the LPT rule, then job D would be completed on day (assume zero for to day’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 5.
b) 25.
c) 30.
d) 33.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
57. If the following jobs are sequenced according to the SLACK rule, then the mean completion time (in days) for all jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 35 days.
b) 19.4 days.
c) 18.4 days.
d) 7 days.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
58. If the following jobs are sequenced according to the SLACK rule, then the mean tardiness (in days) for all jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 11.25 days.
b) 7.8 days.
c) 20 days.
d) 12.5 days.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
59. If the following jobs are sequenced according to the SLACK rule, then the maximum job tardiness (in days) is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 18 days.
b) 12 days.
c) 10 days.
d) 7 days.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
60. If the following jobs are sequenced according to the SLACK rule, then the total number of jobs that would be late is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 1 jobs.
b) 2 jobs.
c) 3 jobs.
d) 4 jobs.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
61. If the following jobs are sequenced according to the SLACK rule, then job A would be completed on day (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 8.
b) 7.
c) 15.
d) 12.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
62. If the following jobs are sequenced according to the DDATE rule, then the mean completion time (in days) for all jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 16.4 days.
b) 22.6 days.
c) 28.7 days.
d) 33.0 days
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
63. If the following jobs are sequenced according to the DDATE rule, then the mean tardiness (in days) for all jobs is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 9.0 days.
b) 5.4 days.
c) 3.2 days.
d) 2.8 days
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
64. If the following jobs are sequenced according to the DDATE rule, then the maximum job tardiness (in days) is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 12 days.
b) 15 days.
c) 16 days.
d) 27 days.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
65. If the following jobs are sequenced according to the DDATE rule, then the total number of jobs that would be late is (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 5 jobs.
b) 4 jobs.
c) 3 jobs.
d) 2 jobs.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
66. If the following jobs are sequenced according to the DDATE rule, then job A would be completed on day (assume zero for today’s date)
Job | Processing Time (days) | Due Date |
A | 8 | 12 |
B | 6 | 15 |
C | 11 | 17 |
D | 5 | 10 |
E | 3 | 8 |
a) 8.
b) 12.
c) 16.
d) 22.
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
67. Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below:
Machine | ||||
Product | A | B | C | D |
1 | 10 | 9 | 16 | 12 |
2 | 8 | 14 | 17 | 5 |
3 | 19 | 20 | 11 | 7 |
4 | 8 | 18 | 5 | 10 |
If management wishes to assign products to machines so that the total time to complete all the products is minimized, then Product 1 is assigned to
a) machine A
b) machine B
c) machine C
d) machine D
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
68. Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below:
Machine | ||||
Product | A | B | C | D |
1 | 10 | 9 | 16 | 12 |
2 | 8 | 14 | 17 | 5 |
3 | 19 | 20 | 11 | 7 |
4 | 8 | 18 | 5 | 10 |
If management wishes to assign products to machines so that the total time to complete all the products is minimized, then Product 3 is assigned to
a) machine A.
b) machine B.
c) machine C.
d) machine D.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
69. Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below.
Machine | ||||
Product | A | B | C | D |
1 | 10 | 9 | 16 | 12 |
2 | 8 | 14 | 17 | 5 |
3 | 19 | 20 | 11 | 7 |
4 | 8 | 18 | 5 | 10 |
If management wishes to assign products to machines so that the total time to complete all the products is minimized, then Product 4 is assigned to
a) machine A.
b) machine B.
c) machine C.
d) machine D.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
70. Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below:
Machine | ||||
Product | A | B | C | D |
1 | 10 | 9 | 16 | 12 |
2 | 8 | 14 | 17 | 5 |
3 | 19 | 20 | 11 | 7 |
4 | 8 | 18 | 5 | 10 |
If management assigns products to machines so that the total time to complete all jobs is minimized, then the time to complete Product 1 is
a) 10 minutes.
b) 9 minutes.
c) 16 minutes.
d) 12 minutes
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
71. Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below:
Machine | ||||
Product | A | B | C | D |
1 | 10 | 9 | 16 | 12 |
2 | 8 | 14 | 17 | 5 |
3 | 19 | 20 | 11 | 7 |
4 | 8 | 18 | 5 | 10 |
The minimum time required to complete all the products is
a) 29 minutes.
b) 27 minutes.
c) 33 minutes.
d) 36 minutes.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
AACSB: Analytic
72. The scheduling rule that minimizes the makespan time for a set of jobs that must be processed through a two-step system where every job follows the same sequence through the two processes is the
a) shortest processing time (SPT).
b) Johnson’s Rule.
c) assignment method.
d) minimal slack rule.
Difficulty: Easy
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Knowledge
AACSB: Reflective Thinking
73. The following set of jobs must be processed serially through a two-step system. If Johnson’s Rule is used to sequence the jobs, then the order in which the jobs would be performed is
Job | Process 1 | Process 2 |
A | 12 | 9 |
B | 8 | 11 |
C | 7 | 6 |
D | 10 | 14 |
E | 5 | 8 |
a) A-B-C-D-E
b) C-B-E-D-A
c) E-B-D-A-C
d) D-E-B-A-C
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
74. The following set of jobs must be processed serially through a two-step system. The times at each process are in hours. If Johnson’s Rule is used to sequence the jobs then the makespan time (in hours) for all jobs is
Job | Process 1 | Process 2 |
A | 12 | 9 |
B | 8 | 11 |
C | 7 | 6 |
D | 10 | 14 |
E | 5 | 8 |
a) 42 hours.
b) 53 hours.
c) 90 hours.
d) 95 hours.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
75. The following set of jobs must be processed serially through a two-step system. The times at each process are in hours. If Johnson’s Rule is used to sequence the jobs then Job C would start processing on operation 2 at
Job | Process 1 | Process 2 |
A | 12 | 9 |
B | 8 | 11 |
C | 7 | 6 |
D | 10 | 14 |
E | 5 | 8 |
a) hour 13.
b) hour 26.
c) hour 47.
d) hour 53.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
76. The following set of jobs must be processed serially through a two-step system. The times at each process are in hours. If Johnson’s Rule is used to sequence the jobs, then Job A would complete processing on operation 2 at
Job | Process 1 | Process 2 |
A | 12 | 9 |
B | 8 | 11 |
C | 7 | 6 |
D | 10 | 14 |
E | 5 | 8 |
a) hour 21.
b) hour 35.
c) hour 38.
d) hour 47.
Difficulty: Hard
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Application
AACSB: Analytic
77. The difference between a job’s due date and its completion time is known as
a) flow time
b) makespan
c) tardiness
d) slack
Difficulty: Medium
Learning Objective: Explain what sequencing is and use rules and quantitative tools for optimizing the sequence of jobs processed through one or two workstations.
Section Reference: 17.3 Sequencing
Blooms: Comprehension
AACSB: Reflective Thinking
78. A ___ chart is used to show both planned and completed activities against a time scale.
a) Gantt
b) Dispatch
c) Sequencing
d) None of the above.
Learning Objective: Use several methods to monitor the progress of jobs in a job shop environment.
Section Reference: 17.4 Monitoring
Blooms: Knowledge
AACSB: Reflective Thinking
79. Shop paperwork that travels with a job is known as a
a) Gantt chart
b) work package
c) bill of materials
d) input/output document
Difficulty: Easy
Learning Objective: Use several methods to monitor the progress of jobs in a job shop environment.
Section Reference: 17.4 Monitoring
Blooms: Knowledge
AACSB: Reflective Thinking
80. A scheduling technique which loads without regards to capacity, then levels the load and sequences the jobs is known as
a) finite scheduling
b) infinite scheduling
c) advanced planning and scheduling
d) load levelling
Difficulty: Easy
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Knowledge
AACSB: Reflective Thinking
81. Which of the following best describes a scheduling technique that sequences jobs as part of the loading decision and where resources are never loaded beyond capacity?
a) finite scheduling
b) infinite scheduling
c) advanced planning and scheduling
d) load levelling
Difficulty: Easy
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Knowledge
AACSB: Reflective Thinking
82. A finite scheduling approach that concentrates on scheduling the bottleneck resource is known as
a) finite scheduling
b) infinite scheduling
c) advanced planning and scheduling
d) theory of constraints
Difficulty: Easy
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Knowledge
AACSB: Reflective Thinking
83. Which of the following is considered one of the most flexible resources?
a) materials
b) labour
c) utilities
d) overhead
Difficulty: Easy
Learning Objective: Use a heuristic to schedule workers and explain the capabilities provided by employee scheduling software.
Section Reference: 17.6 Employee Scheduling
Blooms: Knowledge
AACSB: Reflective Thinking
84. Automated scheduling systems typically include the following features except
a) staff scheduling
b) schedule bidding
c) staff bidding
d) schedule optimization
Learning Objective: Use a heuristic to schedule workers and explain the capabilities provided by employee scheduling software.
Section Reference: 17.6 Employee Scheduling
Blooms: Knowledge
AACSB: Reflective Thinking
SHORT-ANSWER ESSAY QUESTIONS
85. What makes scheduling so difficult in a job shop?
Difficulty: Easy
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Comprehension
AACSB: Reflective Thinking; Communication
86. List some of the objectives in scheduling.
Difficulty: Medium
Learning Objective: Describe scheduling techniques and list the objectives of scheduling.
Section Reference: 17.1 Scheduling Techniques
Blooms: Knowledge
AACSB: Reflective Thinking; Communication
87. Why is monitoring an important component of job-shop scheduling?
Difficulty: Medium
Learning Objective: Use several methods to monitor the progress of jobs in a job shop environment.
Section Reference: 17.4 Monitoring
Blooms: Evaluation
AACSB: Reflective Thinking; Communication
88. What is the difference between infinite and finite scheduling?
Difficulty: Medium
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Evaluation
AACSB: Reflective Thinking; Communication
89. Who developed the theory of constraints (TOC) and what is its approach to scheduling?
Difficulty: Hard
Learning Objective: Explain the basics of finite scheduling, and use the theory of constraints procedure to schedule multiple jobs through multiple workstations.
Section Reference: 17.5 Advanced Planning and Scheduling Systems
Blooms: Compression
AACSB: Reflective Thinking; Communication
90. Discuss some of the complexities involved with scheduling employees in the service firms.
Difficulty: Medium
Learning Objective: Use a heuristic to schedule workers and explain the capabilities provided by employee scheduling software.
Section Reference: 17.6 Employee Scheduling
Blooms: Synthesis
AACSB: Reflective Thinking; Communication
LEGAL NOTICE
Copyright © 2014 by John Wiley & Sons Canada, Ltd. or related companies. All rights reserved.
The data contained in these files are protected by copyright. This manual is furnished under licence and may be used only in accordance with the terms of such licence.
The material provided herein may not be downloaded, reproduced, stored in a retrieval system, modified, made available on a network, used to create derivative works, or transmitted in any form or by any means, electronic, mechanical, photocopying, recording, scanning, or otherwise without the prior written permission of John Wiley & Sons Canada, Ltd.