Winch Ch.11 - The Core Skills Test Bank - Test Bank | Strategic Project Org 1e Winch by Graham Miles Winch. DOCX document preview.

Winch Ch.11 - The Core Skills Test Bank

Chapter 11 - The core skills

Test Bank

Type: true-false

Title: Chapter 11 Question 1

01) It is commonly understood that there is a difference between managers and leaders.

a. True

b. False

Type: true-false

Title: Chapter 11 Question 2

02) Technical competencies largely deployed within the delivery domain need to be understood by project leaders working in the owner and supplier domains.

a. True

b. False

Type: true-false

Title: Chapter 11 Question 3

03) Planning stops at the Define stage as greater levels of detail as the WBS is developed, budgets are finalized and schedule refined.

a. True

b. False

Type: multiple choice question

Title: Chapter 11 Question 4

04) What fundamental question does process of planning answer:

a. What needs to be done in a project?

b. Who will deliver a project?

c. How much will a project cost?

d. How are we going to deliver the outputs specified in the Project Execution Plan?

Type: matching question

Title: Chapter 11 Question 5

05) Earned Value Analysis takes into consideration three measures and questions a project manager asks:

Feedback:

Earned Value Analysis takes into consideration three measures and questions a project manager asks:

  • Earned Value (EV): budgeted cost of work completed at specific point in the schedule. How much work have we actually completed?
  • Actual Cost (AC): actual spend to date. How much did we spend to complete the work?
  • Planned Value (PV): what ought to have been spent at a specific point in the schedule according to the budget. How much work did we plan to complete?

A-head reference: 11.5

a. Earned Value (EV) = Actual spend to date. How much did we spend to complete the work?

b. Actual Cost (AC) = Budgeted cost of work completed at specific point in the schedule. How much work have we actually completed?

c. Planned Value (PV) = What ought to have been spent at a specific point in the schedule according to the budget. How much work did we plan to complete?

Type: matching question

Title: Chapter 11 Question 6

06) We measure execution performance by comparing current performance against the Project Execution Plan. This comparison results in one of the three options for action:

Feedback:

We measure execution performance by comparing current performance against the Project Execution Plan through the information loop. This comparison results in one of the three options for action:

  • Continue with the plan unchanged if performance aligns with the PEP;
  • Take corrective action if the plan and performance do not align;
  • Revise the PEP if the original plan is no longer achievable due to new information becoming available.

A-head reference: 11.5

a. Continue with the plan unchanged = if the original plan is no longer achievable due to new information becoming available.

b. Take corrective action = if performance aligns with the PEP

c. Revise the PEP = if the plan and performance do not align

Type: multiple choice question

Title: Chapter 11 Question 7

07) Graphical scheduling technique that acts as boundary objects between teams:

a. Critical path method

b. Critical chain

c. Gantt charts

d. Critical space analysis

Type: true-false

Title: Chapter 11 Question 8

08) Budget estimation is a linear and completely accurate process carried out at the beginning of a project.

a. True

b. False

Type: matching question

Title: Chapter 11 Question 9

09) Four methods for estimating costs can be broadly identified:

Feedback:

Four methods for estimating costs can be broadly identified:

  • Ballpark, usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points.
  • The PDP, where estimates are established from preliminary engineering work with an accuracy range of approximately70 percentage points.
  • Comparative, where cost estimates are developed by comparing to past similar projects to provide an outside view with the aim of reducing the variance.
  • The PEP which provides estimates based on the work during the Define stage with an accuracy range of approximately38 percentage points.

A-head reference: 11.5

a. Ballpark = where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance

b. The PDP = where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points

c. Comparative = which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points

d. The PEP = usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points

Type: true-false

Title: Chapter 11 Question 10

10) Managing conformance is an iterative process that needs to be tailored to each project.

a. True

b. False

Document Information

Document Type:
DOCX
Chapter Number:
11
Created Date:
Aug 21, 2025
Chapter Name:
Chapter 11 - The Core Skills
Author:
Graham Miles Winch

Connected Book

Test Bank | Strategic Project Org 1e Winch

By Graham Miles Winch

Test Bank General
View Product →

$24.99

100% satisfaction guarantee

Buy Full Test Bank

Benefits

Immediately available after payment
Answers are available after payment
ZIP file includes all related files
Files are in Word format (DOCX)
Check the description to see the contents of each ZIP file
We do not share your information with any third party