Winch Ch.11 - The Core Skills Test Bank - Test Bank | Strategic Project Org 1e Winch by Graham Miles Winch. DOCX document preview.
Chapter 11 - The core skills
Test Bank
Type: true-false
Title: Chapter 11 Question 1
01) It is commonly understood that there is a difference between managers and leaders.
a. True
b. False
Type: true-false
Title: Chapter 11 Question 2
02) Technical competencies largely deployed within the delivery domain need to be understood by project leaders working in the owner and supplier domains.
a. True
b. False
Type: true-false
Title: Chapter 11 Question 3
03) Planning stops at the Define stage as greater levels of detail as the WBS is developed, budgets are finalized and schedule refined.
a. True
b. False
Type: multiple choice question
Title: Chapter 11 Question 4
04) What fundamental question does process of planning answer:
a. What needs to be done in a project?
b. Who will deliver a project?
c. How much will a project cost?
d. How are we going to deliver the outputs specified in the Project Execution Plan?
Type: matching question
Title: Chapter 11 Question 5
05) Earned Value Analysis takes into consideration three measures and questions a project manager asks:
Feedback:
Earned Value Analysis takes into consideration three measures and questions a project manager asks:
- Earned Value (EV): budgeted cost of work completed at specific point in the schedule. How much work have we actually completed?
- Actual Cost (AC): actual spend to date. How much did we spend to complete the work?
- Planned Value (PV): what ought to have been spent at a specific point in the schedule according to the budget. How much work did we plan to complete?
A-head reference: 11.5
a. Earned Value (EV) = Actual spend to date. How much did we spend to complete the work?
b. Actual Cost (AC) = Budgeted cost of work completed at specific point in the schedule. How much work have we actually completed?
c. Planned Value (PV) = What ought to have been spent at a specific point in the schedule according to the budget. How much work did we plan to complete?
Type: matching question
Title: Chapter 11 Question 6
06) We measure execution performance by comparing current performance against the Project Execution Plan. This comparison results in one of the three options for action:
Feedback:
We measure execution performance by comparing current performance against the Project Execution Plan through the information loop. This comparison results in one of the three options for action:
- Continue with the plan unchanged if performance aligns with the PEP;
- Take corrective action if the plan and performance do not align;
- Revise the PEP if the original plan is no longer achievable due to new information becoming available.
A-head reference: 11.5
a. Continue with the plan unchanged = if the original plan is no longer achievable due to new information becoming available.
b. Take corrective action = if performance aligns with the PEP
c. Revise the PEP = if the plan and performance do not align
Type: multiple choice question
Title: Chapter 11 Question 7
07) Graphical scheduling technique that acts as boundary objects between teams:
a. Critical path method
b. Critical chain
c. Gantt charts
d. Critical space analysis
Type: true-false
Title: Chapter 11 Question 8
08) Budget estimation is a linear and completely accurate process carried out at the beginning of a project.
a. True
b. False
Type: matching question
Title: Chapter 11 Question 9
09) Four methods for estimating costs can be broadly identified:
Feedback:
Four methods for estimating costs can be broadly identified:
- Ballpark, usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points.
- The PDP, where estimates are established from preliminary engineering work with an accuracy range of approximately70 percentage points.
- Comparative, where cost estimates are developed by comparing to past similar projects to provide an outside view with the aim of reducing the variance.
- The PEP which provides estimates based on the work during the Define stage with an accuracy range of approximately38 percentage points.
A-head reference: 11.5
a. Ballpark = where cost estimates are developed by comparing to past similar projects to provide outside view with the aim of reducing the variance
b. The PDP = where estimates are established from preliminary engineering work with an accuracy range of approx.70 percentage points
c. Comparative = which provides estimates based on the work during the Define stage with an accuracy range of approx.38 percentage points
d. The PEP = usually used early in the life cycle when there is very limited information or time to prepare with an accuracy range of approx.90 percentage points
Type: true-false
Title: Chapter 11 Question 10
10) Managing conformance is an iterative process that needs to be tailored to each project.
a. True
b. False