Chapter.5 Scheduling the Project Exam Questions 6th Edition - Project Management Practice 6e Complete Test Bank by Jack R. Meredith. DOCX document preview.

Chapter.5 Scheduling the Project Exam Questions 6th Edition

Chapter 5: Scheduling the Project

True/False

1. When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.

Response: See section 5.1

Level: medium

2. AON and AOA networks can both be used to depict any project network.

Response: See section 5.1

Level: medium

3. The shortest time to complete a network is equal to the duration of the longest path through the network.

Response: See section 5.1

Level: medium

4. Critical path tasks always have zero slack.

Response: See section 5.1

Level: medium

5. To manage a project successfully, the project manager need only pay close attention to tasks on the critical path.

Response: See section 5.1

Level: medium

6. “Merger” is a term used to describe the situation in which two or more paths in a network join together.

Response: See section 5.2

Level: easy

7. If task duration estimates are carefully made, the project manager needs to only examine the critical path when conducting a risk analysis.

Response: See section 5.2

Level: medium

8. The actual project duration will be known with certainty after the project is completed.

Response: See section 5.3

Level: medium

9. Milestones cannot be identified on a Gantt Chart.

Response: See section 5.4

Level: medium

10. It is easiest to see lead and lag time in a project task on a PERT/CPM networks.

Response: See section 5.5

Level: medium

11. A start-to-finish linkage is the most common way of linking to successive task.

Response: See section 5.5

Level: medium

12. The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a Beta distribution.

Response: See section 5.2

Level: medium

13. A project schedule is a project action plan converted into a timetable.

Response: See section 5.1

Level: medium

14. A Gantt chart cannot depict a critical path, only a PERT/CPM chart can.

Response: See section 5.4

Level: medium

15. The difference between the LST and EST is called slack.

Response: See section 5.1

Level: medium

16. A disadvantage of Gantt charts is that they are hard to draw.

Response: See section 5.4

Level: medium

17. The difference between LST and LFT is called slack.

Response: See section 5.1

Level: medium

18. Standard Pert/CPM networks can be use to resolve probabilistic concerns.

Response: See section 5.1

Level: medium

19. Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.

Response: See section 5.4

Level: medium

20. The difference between EST and LFT is called slack.

Response: See section 5.1

Level: medium

21. The difference between LFT and EFT is called slack.

Response: See section 5.1

Level: medium

22. A big advantage of AON networks is that they are easier to draw.

Response: See section 5.1

Level: medium

23. The tasks of project planning, project budgeting, and project scheduling are largely separable from one another.

Response: See section 5.1

Level: medium

24. An event is a series of connected activities.

Response: See section 5.1

Level: easy

25. A disadvantage of using beta distribution to approximate activity times is that it is generally less flexible than the normal distribution.

Response: See section 5.2

Level: medium

26. The simulation approach is generally preferred over the statistical method.

Response: See section 5.3

Level: medium

27. Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks.

Response: See section 5.3

Level: medium

28. The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.

Response: See section 5.5

Level: medium

29. Milestones are not depended upon the predecessor activities in the project plan.

Response: See section 5.1

Level: medium

30. Another name for total slack is free slack.

Response: See section 5.1

Level: medium

31. A diagram of nodes connected by directional arcs that defines the project and illustrates the technical of all activities is referred to as a network.

Response: See section 5.1

Level: medium

32. Networks are usually drawn with a “Start” node to the right and a “Finish” node to the left.

Response: See section 5.1

Level: medium

33. A situation where two or more activities have the same starting and finishing nodes or where a single activity connects to two or more nodes is called a dummy task

Response: See section 5.1

Level: medium

34. The movement from left to right through the network beginning with the start node that calculates the LS and LF for each activity is known as “FORWARD PASS”

Response: See section 5.1

Level: medium

35. Float refers to the amount of time a noncritical task can be delayed without causing a delay in the entire project.

Response: See section 5.1

Level: medium

36. The amount of time an activity can be delayed without affecting the start time of any successor activity is known as free slack.

Response: See section 5.1

Level: easy

37. Events in a project consume no resources or time.

Response: See section 5.1

Level: medium

Multiple Choice

38. Technical dependencies on a project plan are easiest to see on a:

a) Gantt chart

b) Cost chart

c) PERT/CPM chart

d) Work Breakdown Structure

e) RACI Matrix

Response: See section 5.4

Level: medium

39. PERT was originally used for what type of project?

a) construction

b) R & D

c) military

d) computer software development

e) advertising

Response: See section 5.1

Level: medium

40. Which of the following terms is most closely associated with a task required by the project?

a) activity

b) event

c) milestone

d) network

e) path

Response: See section 5.1

Level: easy

41. What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively?

a) 3

b) 4

c) 4.3

d) 4.7

e) 7

Response: See section 5.2

Level: medium

42. What is the standard deviation of a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively assuming the estimates were made at the 99% plus level?

a) .444

b) .667

c) 1.212

d) 1.469

e) 1.540

Response: See section 5.2

Level: medium

43. The amount of time a noncritical task can be delayed without delaying the project is called?

a) surplus

b) flop

c) slack

d) critical time

e) safety

Response: See section 5.1

Level: medium

44. Slack is calculated as?

a) LFT - EST

b) LFT - LST

c) LST - LFT

d) LFT - EFT

e) EFT - EST

Response: See section 5.1

Level: medium

45. A Term not used in the discussion of PERT/CPM analysis is

a) Activity

b) Events

c) Critical Path

d) Sensitivity path

e) network s

Response: See section 5.1

Level: medium

46. An identifiable state resulting from the completion of one or more activities is called?

a) an event

b) an activity

c) a milestone

d) a path

e) the critical path

Response: See section 5.1

Level: medium

47. Organ Bennett Inc., a public relations firm, is working on a project to improve the brand image of Sizil, a client firm, over a period of a year. The project requires Organ Bennett to organize a press conference to announce the launch of Sizil's new product. The project members need to invite reporters for the same. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), inviting reporters is most likely a(n) _____.

a) event

b) activity

c) network

d) milestone

e) float

Response: See section 5.1

Level: difficult

48. Rico Gen, a sports apparel manufacturing company, maintains a target of increasing its sales by 20 percent per month to achieve its goal of expanding its business in the international market. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), the monthly targets achieved by Rico Gen are known as _____.

a) activities

b) floats

c) activity slacks

d) milestones

e) paths

Response: See section 5.1

Level: difficult

49. Paul, the marketing manager of a food company, created a diagram of nodes to represent the marketing process for a new product of the company. Each node represented an activity in the marketing process, and an arc joined each node. He used this diagram to demonstrate the objectives of the marketing process. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), the diagram used by Paul is known as a _____.

a) network

b) flowchart

c) Gantt chart

d) Smith chart

e) control chart

Response: See section 5.1

Level: difficult

50. Verita Nist, an automobile company, sought to improve the production time and quality of its products within a year. In the first month, the company installed five new assembling machines. This reduced the production time by 15 percent. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), this decrease in the production time of Verita Nist's products is an example of a(n) _____.

a) task

b) activity

c) critical path

d) event

e) throughput

Response: See section 5.1

Level: difficult

51. Minkset Blu, a textile company, wants to improve its sales over a span of four years. In the first year, the company installs new looming machines that improve the production cost. However, it takes two years for the company to establish a liaison with online retailers to improve the accessibility of its products. This delays the company's goal of improving sales by a year. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM), the set of activities that cause the delay are part of _____.

a) the Smith chart

b) the Portolan chart

c) the critical path

d) the throughput process

e) the control chart

Response: See section 5.1

Level: difficult

52. Nessage Mique, a niche fashion boutique, displays its production process by using a network of nodes and arrows. The nodes are used to depict the state of completion of various activities and the arrows are used to depict their order of precedence. Which of the following project networks is Nessage Mique using in the given scenario?

a) An event-on-arrow network

b) A time-on-arrow network

c) An activity-on-node network

d) A time-on-node network

e) An activity-on-arrow network

Response: See section 5.1

Level: difficult

53. Miros Inc., a recording studio, displays its recording process by using a network of nodes and arrows. The nodes are used to depict the activities involved in recording a song, such as setting up the instruments, and the arrows are used to depict the order of precedence of the activities. Which of the following project networks is Miros using in the given scenario?

a) A time-on-node network

b) An activity-on-arrow network

c) A time-on-arrow network

d) An activity-on-node network

e) An event-on-node network

Response: See section 5.1

Level: difficult

54. Ben is part of a new project in his company. He is asked to complete a task within two days, but he is only able to finish it in three days. Since the task assigned to him is noncritical in nature, the extra day taken by Ben does not cause a delay in the project. In this scenario, the additional day taken by Ben is known as _____.

a) flow time

b) throughput

c) slack

d) critical time

e) flowgrind

Response: See section 5.1

Level: difficult

55. Consider a project network that begins with activity A and is followed by activity B. Activity A takes 6 days to finish. If the earliest start time for activity B is 6 days and the latest start time for it is 10 days, activity B has a slack of _____.

a) 16 days

b) 4 days

c) 10 days

d) 2 days

e) 12 days

Response: See section 5.1

Level: difficult

56. Consider a project network that begins with activity X and is followed by activity Y. The earliest start time for activity X is 5 days and it will take 3 days to be completed. The earliest start time for activity Y is 12 days. Given this information, activity X has _____ of free slack.

a) 20 days

b) 4 days

c) 12 days

d) 9 days

e) 15 days

Response: See section 5.1

Level: difficult

Short Answer

57. Define the term critical path.

Response: See section 5.1

Level: easy

58. What is activity slack?

Response: See section 5.1

Level: easy

59. What is a Gantt chart?

Response: See section 5.4

Level: easy

60. What are the four methods of linking steps in a project using precedence diagramming?

Response: See section 5.5

Level: easy

61. Contrast total slack and free slack.

Response: See section 5.1

Level: medium

62. Contrast the traditional statistical approach to calculating the probability of completing a project by a specified time with the simulation approach.

Response: See section 5.2

Level: medium

63. Why should we only draw the Gantt chart after we have drawn the network for the project?

Response: See section 5.4

Level: medium

64. What assumptions are made about the probabilities of the optimistic and pessimistic times in the standard formula for calculating the variance of a particular activity? Explain how the formula can be modified to accommodate different assumptions.

Response: See section 5.2

Level: medium

65. Explain why the term critical path has less meaning in cases where the activity times are not known with certainty.

Response: See section 5.2

Level: medium

66. What is a merger and what problems do mergers create?

Response: See section 5.2

Level: medium

67. Why is it necessary for the project manager (PM) to be aware and to manage the slack in the project?

Response: See section 5.1

Level: medium

Document Information

Document Type:
DOCX
Chapter Number:
5
Created Date:
Aug 21, 2025
Chapter Name:
Chapter 5 Scheduling the Project
Author:
Jack R. Meredith

Connected Book

Project Management Practice 6e Complete Test Bank

By Jack R. Meredith

Test Bank General
View Product →

$24.99

100% satisfaction guarantee

Buy Full Test Bank

Benefits

Immediately available after payment
Answers are available after payment
ZIP file includes all related files
Files are in Word format (DOCX)
Check the description to see the contents of each ZIP file
We do not share your information with any third party